[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-386119":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},386119,167,1,"单选题","在进行进度计划编制时，第一步是（ ）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目描述",true,{"key":16,"text":17,"correct":18},"B","项目分解",false,{"key":20,"text":21,"correct":18},"C","收集信息",{"key":23,"text":24,"correct":18},"D","召开会议","计划编制步骤第一步：项目描述第二步：项目分解第三步：工作描述第四步：工作责任分配表制定第五步：工作先后关系确定第六步：绘制网络图第七步：工作时间估计第八步：进度安排",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 信息系统监理师","职业资格",0]