[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-386116":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},386116,167,1,"单选题","下图是典型的“香蕉”曲线法其中曲线A表示的是（ ）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","最合理时间计划",false,{"key":16,"text":17,"correct":14},"B","最优时间计划",{"key":19,"text":20,"correct":21},"C","最早时间计划",true,{"key":23,"text":24,"correct":14},"D","最迟时间计划","图中曲线A为最早时间计划，曲线B为最迟时间计划，曲线N为实际进度。曲线N处在两曲线之中，表示进度正常，处于曲线A之上，表示提前，处于曲线B之下为延期。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 信息系统监理师","职业资格",0]