[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-386111":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},386111,167,1,"单选题","以下（ ）不是信息系统工程项目进度控制的总目标",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目越早完成越好",true,{"key":16,"text":17,"correct":18},"B","在计划规定的时间内完成",false,{"key":20,"text":21,"correct":18},"C","信息系统达到竣工验收、试运行及投入使用的计划时间",{"key":23,"text":24,"correct":18},"D","当进度出现偏差时应及时采取整改措施，并使项目回归正常轨道","记住一点，项目并非是越早完成越好，例如一味追求进度的提前往往有可能会导致质量的下降，或者为了追求进度同时又抓质量，就需要投入几倍的人力、物力，则导致成本的追加。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 信息系统监理师","职业资格",0]