[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-386109":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},386109,167,1,"单选题","进度控制的基本程序和主要措施不包括：",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","组织措施",false,{"key":16,"text":17,"correct":14},"B","经济措施",{"key":19,"text":20,"correct":14},"C","合同措施",{"key":22,"text":23,"correct":24},"D","风险措施",true,"进度控制的基本程序和主要措施包括：组织措施。落实监理单位进度控制的人员组成，具体控制任务和管理职责分工。经济措施。做好工期惩罚或奖励，把控付款签认。技术措施。确定合理定额，进行进度预测分析和进度统计。合同措施。合同期与进度协调。信息管理措施。实行计算机进度动态比较，提供比较报告。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 信息系统监理师","职业资格",0]