[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-386097":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},386097,167,1,"单选题","以下关于工程设计阶段质量控制的要点及方法中，说法错误的是（ ）",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","了解建设单位建设需求和对信息系统安全性的要求，协助建设单位制定项目质量目标规划和安全目标规划。",false,{"key":16,"text":17,"correct":14},"B","对各种设计文件，提出设计质量标准",{"key":19,"text":20,"correct":14},"C","审查阶段性设计成果，并提出监理意见",{"key":22,"text":23,"correct":24},"D","进行设计过程跟踪，及时发现质量问题，并及时下达监理通知书，责令承建单位进行修改完善",true,"进行设计过程跟踪，及时发现质量问题，并及时与承建单位协调解决。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 信息系统监理师","职业资格",0]