[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-386076":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},386076,167,1,"单选题","在监理合同签订之后应该由（ ）编制监理规划",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","公司总监",false,{"key":16,"text":17,"correct":18},"B","项目总监",true,{"key":20,"text":21,"correct":14},"C","总监代表",{"key":23,"text":24,"correct":14},"D","资深监理工程师","公司总监负责对所有项目总监进行协调、管理，例如安排张三担任A项目的项目总监理工程师，李四担任B项目的项目总监理工程师。张三、李四应对各自负责的监理项目负主要责任，并定期将各自项目监理工作情况向公司总监汇报。因此无论是A项目还是B项目的监理规划，都应由各自项目的总监理工程师负责编制。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 信息系统监理师","职业资格",0]