[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-385856":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},385856,166,1,"单选题","制定系统运行计划之前，工作小组成员要先了解单位现有软、硬件和所有工作人员的技术水平及其对旧系统的熟悉情况，并充分学习和掌握新系统的功能和特性，结合本单位的实际情况制定新系统的运行计划。下列选项中，（ ）不应在计划内容之列。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","运行开始的时间",false,{"key":16,"text":17,"correct":14},"B","运行周期",{"key":19,"text":20,"correct":21},"C","开发小组人员的安排",true,{"key":23,"text":24,"correct":14},"D","运行管理制度","本题考查对制定系统运行计划的工作内容的理解。?系统运行计划的内容包括：运行开始的时间、运行周期、运行环境、运行管理的组织机构、系统数据的管理、运行管理制度、系统运行结果分析等，它不涉及开发小组人员的安排。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 信息系统管理工程师","职业资格",0]