[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-385690":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},385690,166,1,"单选题","以下关于系统切换的叙述中，正确的是（ ）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","系统切换的任务是保证新、老系统进行平稳而可靠的交接",true,{"key":16,"text":17,"correct":18},"B","直接切换的风险最小",false,{"key":20,"text":21,"correct":18},"C","系统切换只需要操作人员独立完成",{"key":23,"text":24,"correct":18},"D","新系统通过测试后就可以直接投入正常运行","（1）直接转换，在确定系统准确无误后，用新系统直接替换旧系统，终止旧系统运行，中间没有过度阶段。（2）试点后直接转换，某些系统有一些相同部分，转换时选择一个作为试点，试点成功后，其他部分可以同时进行直接转换。（3）逐步转换，分期分批的进行转换。（4）并行转换，安排一段新旧系统并行运行的时期，直到新系统正常运行有保证时，才停止旧系统运行。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 信息系统管理工程师","职业资格",0]