[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-385426":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},385426,166,1,"单选题","以下关于信息系统项目的说法中，不正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","信息系统项目的目标明确，任务边界清晰",true,{"key":16,"text":17,"correct":18},"B","信息系统开发过程中客户需求会随项目进展而变化",false,{"key":20,"text":21,"correct":18},"C","信息系统项目是智力密集、劳动密集型项目",{"key":23,"text":24,"correct":18},"D","项目成员结构、责任心和能力对信息系统项目的质量有决定性影响","信息系统项目独有的特点?项目的目标不精确、任务边界模糊、质量要求主要由项目团队定义。开发过程中，客户的需求不断被激发、不断地被进一步明确、客户需求随项目进展而变化、项目的进度、费用等计划会不断更改。?信息系统项目是智力密集、劳动密集型项目，受人力资源影响最大，项目团队的结构、责任心和稳定性对项目的质量和是否成功有决定性的影响。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 信息系统管理工程师","职业资格",0]