[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-385419":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},385419,166,1,"单选题","某软件项目的活动图如下图所示，其中顶点表示项目里程碑，连接顶点的边表示包含的活动，边上的数字表示活动的持续时间（天），则完成该项目的最少时间为，（ ）天。活动FG的松驰时间为（请作答此空）天。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","9",false,{"key":16,"text":17,"correct":14},"B","10",{"key":19,"text":20,"correct":21},"C","18",true,{"key":23,"text":24,"correct":14},"D","26","松弛时间:表示在不影响整个工期的前提下,完成该任务有多少机动余地。关键路径:在Pert图中时间跨度最长的路径",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 信息系统管理工程师","职业资格",0]