[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-385397":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},385397,166,1,"单选题","某软件项目的活动图如下图所示，其中顶点表示项目里程碑，链接顶点的边表示包含的活动，变色数字表示活动的持续时间（天）。完成该项目的最少时间为（ ）天。由于某种原因，现在需要同一个开发人员完成BC和B D，则完成该项目的最少时间为（请作答此空）天。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","11",false,{"key":16,"text":17,"correct":14},"B","18",{"key":19,"text":20,"correct":21},"C","20",true,{"key":23,"text":24,"correct":14},"D","21","找出关键路径即可BC、BD并行，势必会造成两天的时间延误，故项目最少完成时间变为18+2=20天。 第一问是求关键路径 第二问是在关键路径上有活动延期后势必会造成整个项目工期延误",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 信息系统管理工程师","职业资格",0]