[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-385394":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},385394,166,1,"单选题","以下不属于项目成本管理的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","资源计划",false,{"key":16,"text":17,"correct":14},"B","成本预算",{"key":19,"text":20,"correct":21},"C","质量保证",true,{"key":23,"text":24,"correct":14},"D","成本控制","项目成本管理?要保证项目在批准的预算内完成，包括：?资源计划：决定为执行项目活动所需要的资源的种类（人员、设备、材料）和数量。?成本估算：对于为了完成项目活动所需资源的成本进行估计?成本预算：把估算的总成本分配到每一个工作活动中成本控制：控制项目预算的变更",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 信息系统管理工程师","职业资格",0]