[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"lib-165-10":3},{"library":4,"page":9,"limit":10,"total":11,"questions":12,"related":610},{"id":5,"name":6,"category":7,"favorite":8},165,"(中级) 系统集成项目管理工程师","职业资格",0,10,50,1397,[13,34,46,58,70,82,93,105,117,129,141,153,165,177,189,200,212,224,235,247,258,269,281,290,302,314,326,338,350,361,373,384,396,408,420,432,444,456,468,479,491,503,515,527,539,551,563,574,586,598],{"id":14,"libraryId":5,"type":15,"typeLabel":16,"stem":17,"options":18,"answer":20,"analysis":33},384376,1,"单选题","项目计划的编制是一个逐步的过程。以下关于项目计划编制的叙述中，（ ） 是正确的。",[19,23,27,30],{"key":20,"text":21,"correct":22},"A","项目计划的编制过程是渐进明细、逐步细化的过程",true,{"key":24,"text":25,"correct":26},"B","一般进度计划应写在项目主计划中，而其他方面的计划，如范围、质量、成本等应单独编制成子计划",false,{"key":28,"text":29,"correct":26},"C","项目计划只供项目组内部使用，因此客户不必参与项目计划的编制",{"key":31,"text":32,"correct":26},"D","项目经理对项目计划有最高管理权限，可随时修改项目计划","",{"id":35,"libraryId":5,"type":15,"typeLabel":16,"stem":36,"options":37,"answer":28,"analysis":33},384377,"某大型信息系统集成项目组建了一个变更控制委员会来负责项目变更请求的审查与处理工作，并且确立了支配其运作的具体程序和规则。这个程序要求所有得到批准的变更都必须反映到 （ ） 中。",[38,40,42,44],{"key":20,"text":39,"correct":26},"业绩衡量基准",{"key":24,"text":41,"correct":26},"变更管理计划",{"key":28,"text":43,"correct":22},"质量管理计划",{"key":31,"text":45,"correct":26},"质量保证计划",{"id":47,"libraryId":5,"type":15,"typeLabel":16,"stem":48,"options":49,"answer":20,"analysis":33},384378,"为项目选择特定的生命周期模型-般是( )中的工作。",[50,52,54,56],{"key":20,"text":51,"correct":22},"项目管理计划编制",{"key":24,"text":53,"correct":26},"项目章程",{"key":28,"text":55,"correct":26},"项目任务书",{"key":31,"text":57,"correct":26},"质量计划编制",{"id":59,"libraryId":5,"type":15,"typeLabel":16,"stem":60,"options":61,"answer":24,"analysis":33},384379,"某项目经理正在为一个新产品开发项目制订项目管理计划，他应该遵循的基本原则中不包括 （ ） 。",[62,64,66,68],{"key":20,"text":63,"correct":26},"逐步精确细化",{"key":24,"text":65,"correct":22},"技术工作与管理工作相分离",{"key":28,"text":67,"correct":26},"各干系人参与",{"key":31,"text":69,"correct":26},"对相关人员与资源统一组织及管理",{"id":71,"libraryId":5,"type":15,"typeLabel":16,"stem":72,"options":73,"answer":28,"analysis":33},384380,"项目经理在编制项目管理计划时，应 （ ） 。",[74,76,78,80],{"key":20,"text":75,"correct":26},"越简单越好",{"key":24,"text":77,"correct":26},"越详细越好",{"key":28,"text":79,"correct":22},"逐步细化",{"key":31,"text":81,"correct":26},"按照公司的模板编制，不能变更",{"id":83,"libraryId":5,"type":15,"typeLabel":16,"stem":84,"options":85,"answer":20,"analysis":33},384381,"（）是正式批准一个项目的文档，或者是批准现行项目是否进入下一阶段的文档。",[86,87,89,91],{"key":20,"text":53,"correct":22},{"key":24,"text":88,"correct":26},"项目合同",{"key":28,"text":90,"correct":26},"项目启动文档",{"key":31,"text":92,"correct":26},"项目工作说明书",{"id":94,"libraryId":5,"type":15,"typeLabel":16,"stem":95,"options":96,"answer":28,"analysis":33},384382,"某公司要开发一款电子行车记录仪，成立了产品研发项目团队，发布了项目章程，其中不应包括 （ ） 。",[97,99,101,103],{"key":20,"text":98,"correct":26},"开发电子行车记录仪的背景、目的及可行性",{"key":24,"text":100,"correct":26},"业务要求或产品需求",{"key":28,"text":102,"correct":22},"详细的开发计划和投资预算",{"key":31,"text":104,"correct":26},"任命的项目经理和他的权限级别",{"id":106,"libraryId":5,"type":15,"typeLabel":16,"stem":107,"options":108,"answer":31,"analysis":33},384383,"通常在（ ）任命项目经理比较合适",[109,111,113,115],{"key":20,"text":110,"correct":26},"可研过程之前",{"key":24,"text":112,"correct":26},"签订合同之前",{"key":28,"text":114,"correct":26},"招投标之前",{"key":31,"text":116,"correct":22},"开始制定项目计划前",{"id":118,"libraryId":5,"type":15,"typeLabel":16,"stem":119,"options":120,"answer":31,"analysis":33},384384,"通常，项目整体管理变更控制流程是：受理变更申请→（ ）→变更结果追踪与审核",[121,123,125,127],{"key":20,"text":122,"correct":26},"接收或拒绝变更→执行变更→变更的整体影响分析",{"key":24,"text":124,"correct":26},"变更的整体影响分析→执行变更→接收或拒绝变更",{"key":28,"text":126,"correct":26},"执行变更→变更的整体影响分析→接收或拒绝变更",{"key":31,"text":128,"correct":22},"变更的整体影响分析→接收或拒绝变更→执行变更",{"id":130,"libraryId":5,"type":15,"typeLabel":16,"stem":131,"options":132,"answer":20,"analysis":33},384385,"以下各项中， （ ） 不是整体变更控制的输入。",[133,135,137,139],{"key":20,"text":134,"correct":22},"己批准的纠正措施",{"key":24,"text":136,"correct":26},"己完成的可交付物",{"key":28,"text":138,"correct":26},"实际的绩效数据",{"key":31,"text":140,"correct":26},"己批准的项目管理计划",{"id":142,"libraryId":5,"type":15,"typeLabel":16,"stem":143,"options":144,"answer":24,"analysis":33},384386,"整体变更控制过程基于项目的执行情况对项目的过程进行控制。以下关于整体变更控制的描述，()是不恰当的。",[145,147,149,151],{"key":20,"text":146,"correct":26},"每一个变更都需要跟踪和确认",{"key":24,"text":148,"correct":22},"设置多个变更控制委员会",{"key":28,"text":150,"correct":26},"变更过程需要维持所有基线的完整",{"key":31,"text":152,"correct":26},"整体变更控制在不同层次上实施",{"id":154,"libraryId":5,"type":15,"typeLabel":16,"stem":155,"options":156,"answer":28,"analysis":33},384387,"项目章程是正式批准一个项目的文档，项目章程的内容不包括 （ ） 。",[157,159,161,163],{"key":20,"text":158,"correct":26},"项目的目的或项目立项的理由",{"key":24,"text":160,"correct":26},"概要的里程碑进度计划",{"key":28,"text":162,"correct":22},"项目工作的分解方式",{"key":31,"text":164,"correct":26},"概要预算",{"id":166,"libraryId":5,"type":15,"typeLabel":16,"stem":167,"options":168,"answer":31,"analysis":33},384388,"以下关于项目管理计划的叙述中， （ ） 是不正确的。",[169,171,173,175],{"key":20,"text":170,"correct":26},"项目管理范围计划是项目管理团队确认、记录、核实项目范围的指南",{"key":24,"text":172,"correct":26},"项目管理计划可以是粗略的、非正式的文档",{"key":28,"text":174,"correct":26},"项目管理计划是其他知识域中相关分计划的集合",{"key":31,"text":176,"correct":22},"项目管理范围计划仅仅是项目经理确认、管理和控制项目范围的指南",{"id":178,"libraryId":5,"type":15,"typeLabel":16,"stem":179,"options":180,"answer":20,"analysis":33},384389,"（ ） 不属于项目章程的组成内容。",[181,183,185,187],{"key":20,"text":182,"correct":22},"工作说明书",{"key":24,"text":184,"correct":26},"指定项目经理授权",{"key":28,"text":186,"correct":26},"项目概算",{"key":31,"text":188,"correct":26},"项目需求",{"id":190,"libraryId":5,"type":15,"typeLabel":16,"stem":191,"options":192,"answer":31,"analysis":33},384390,"以下关于项目管理计划的叙述中，（）是不正确的",[193,195,197,198],{"key":20,"text":194,"correct":26},"项目范围管理计划是项目管理团队确认，记录，核实项目范围的指南",{"key":24,"text":196,"correct":26},"项目管理计划可以是粗略的，非正式的文档",{"key":28,"text":174,"correct":26},{"key":31,"text":199,"correct":22},"项目范围管理计划仅仅是项目经理确认、管理和控制项目范围的指南",{"id":201,"libraryId":5,"type":15,"typeLabel":16,"stem":202,"options":203,"answer":24,"analysis":33},384391,"在项目整体管理过程中监督和控制项目是一个关键环节，下列不属于监督和控制过程组的是()",[204,206,208,210],{"key":20,"text":205,"correct":26},"客户等项目干系人正式验收并接受已完成的项目可交付物的过程",{"key":24,"text":207,"correct":22},"企业质量管理体系审计",{"key":28,"text":209,"correct":26},"在管理项目团队时，项目经理与组员就组员情况进行正式交谈",{"key":31,"text":211,"correct":26},"编制绩效报告",{"id":213,"libraryId":5,"type":15,"typeLabel":16,"stem":214,"options":215,"answer":28,"analysis":33},384392,"项目章程在项目管理中起着非常重要的作用，以下对项目章程的描述中 （ ） 是错误的。",[216,218,220,222],{"key":20,"text":217,"correct":26},"项目章程应该由项目团队之外的人发布",{"key":24,"text":219,"correct":26},"项目章程使项目与执行组织的日常活动联系起来",{"key":28,"text":221,"correct":22},"项目章程不包括干系人的需求和期望",{"key":31,"text":223,"correct":26},"项目章程包括论证项目的业务方案",{"id":225,"libraryId":5,"type":15,"typeLabel":16,"stem":226,"options":227,"answer":24,"analysis":33},384393,"经项目各有关干系人同意的 （）就是项目的基准，为项目的执行、监控和变更提供了基础。",[228,230,232,233],{"key":20,"text":229,"correct":26},"项目合同书",{"key":24,"text":231,"correct":22},"项目管理计划",{"key":28,"text":53,"correct":26},{"key":31,"text":234,"correct":26},"项目范围说明书",{"id":236,"libraryId":5,"type":15,"typeLabel":16,"stem":237,"options":238,"answer":24,"analysis":33},384394,"反映了信息系统集成项目的技术过程和管理过程的正确顺序 。",[239,241,243,245],{"key":20,"text":240,"correct":26},"制定业务发展计划、实施项目、项目需求分析",{"key":24,"text":242,"correct":22},"制定业务发展计划、项目需求分析、制定项目管理计划",{"key":28,"text":244,"correct":26},"制定业务发展计划、制定项目管理计划、项目需求分析",{"key":31,"text":246,"correct":26},"制定项目管理计划、项目需求分析、制定业务发展计划",{"id":248,"libraryId":5,"type":15,"typeLabel":16,"stem":249,"options":250,"answer":20,"analysis":33},384395,"以下各项中，（）不是整体变更控制的输入。",[251,253,255,256],{"key":20,"text":252,"correct":22},"已批准的纠正措施",{"key":24,"text":254,"correct":26},"已完成的可交付物",{"key":28,"text":138,"correct":26},{"key":31,"text":257,"correct":26},"已批准的项目管理计划",{"id":259,"libraryId":5,"type":15,"typeLabel":16,"stem":260,"options":261,"answer":24,"analysis":33},384396,"承建方项目经理向监理方提交正式审核所用的项目管理计划。其中必须要包括（）",[262,264,265,267],{"key":20,"text":263,"correct":26},"范围管理计划",{"key":24,"text":43,"correct":22},{"key":28,"text":266,"correct":26},"人力资源管理计划",{"key":31,"text":268,"correct":26},"成本管理计划",{"id":270,"libraryId":5,"type":15,"typeLabel":16,"stem":271,"options":272,"answer":20,"analysis":33},384397,"在编制项目管理计划时，项目经理应遵循编制原则和要求，使项目计划符合项目实际管理的需要。以下关于项目管理计划的叙述中， （ ） 是不正确的。",[273,275,277,279],{"key":20,"text":274,"correct":22},"应由项目经理独立进行编制",{"key":24,"text":276,"correct":26},"可以是概括的",{"key":28,"text":278,"correct":26},"项目管理计划可以逐步精确",{"key":31,"text":280,"correct":26},"让干系人参与项目计划的编制",{"id":282,"libraryId":5,"type":15,"typeLabel":16,"stem":283,"options":284,"answer":28,"analysis":33},384398,"某公司正在启动一个新的系统集成项目，任命张某为项目负责人，并从多个职能部门抽调人员组成项目团队，采用矩阵式管理模式。张某认识到在这种情况下团队成员对职能经理的配合往往要超过对自己的配合，因此决定请求公司发布一份 （ ） 。",[285,286,287,288],{"key":20,"text":266,"correct":26},{"key":24,"text":231,"correct":26},{"key":28,"text":53,"correct":22},{"key":31,"text":289,"correct":26},"沟通管理计划",{"id":291,"libraryId":5,"type":15,"typeLabel":16,"stem":292,"options":293,"answer":24,"analysis":33},384399,"在系统集成工程建设项目的网络计划图中，关键路径是指（ ）。",[294,296,298,300],{"key":20,"text":295,"correct":26},"由图中关键节点组成的路径",{"key":24,"text":297,"correct":22},"图中总的工作持续时间最长的路径",{"key":28,"text":299,"correct":26},"图中包含虚箭线且由关键节点组成的路径",{"key":31,"text":301,"correct":26},"图中无虚箭线的路径",{"id":303,"libraryId":5,"type":15,"typeLabel":16,"stem":304,"options":305,"answer":20,"analysis":33},384400,"某项目经理2015年6月1日为止的成本执行（绩效）数据为：PV（计划 值）=20000元，EV（挣值）=21000元。AC（实际成本）=22000元。则SV（进度偏差）是（ ）元",[306,308,310,312],{"key":20,"text":307,"correct":22},"1000",{"key":24,"text":309,"correct":26},"-1000",{"key":28,"text":311,"correct":26},"2000",{"key":31,"text":313,"correct":26},"-2000",{"id":315,"libraryId":5,"type":15,"typeLabel":16,"stem":316,"options":317,"answer":28,"analysis":33},384401,"活动排序的工具和技术有多种，工具和技术的选取由若干因素决定。如果项目经理决定在进度计划编制中使用子网络模板，这个决策意味着（ ）。",[318,320,322,324],{"key":20,"text":319,"correct":26},"该工作非常独特，在不同的阶段需要专门的网络图",{"key":24,"text":321,"correct":26},"在现有的网络上具有可以获取的资源管理软件",{"key":28,"text":323,"correct":22},"在项目中包含几个相同或几乎相同的内容",{"key":31,"text":325,"correct":26},"项目中存在多条关键路径",{"id":327,"libraryId":5,"type":15,"typeLabel":16,"stem":328,"options":329,"answer":20,"analysis":33},384402,"在进度控制中使用假设情景分析的目的是（）。",[330,332,334,336],{"key":20,"text":331,"correct":22},"评审各种情景，使进度与计划保持一致",{"key":24,"text":333,"correct":26},"记录请求的变更",{"key":28,"text":335,"correct":26},"针对何时应更新进度基准，提供额外详情",{"key":31,"text":337,"correct":26},"更新活动属性",{"id":339,"libraryId":5,"type":15,"typeLabel":16,"stem":340,"options":341,"answer":31,"analysis":33},384403,"某公司与客户签订了一个系统集成项目合同，对于项目的范围和完成时间做出了明确的规定。在制定进度计划时，项目经理发现按照估算的活动时间和资源编制的进度计划无法满足合同工期，为了达到合同要求，项目经理不宜采用的方法是 （ ） 。",[342,344,346,348],{"key":20,"text":343,"correct":26},"赶工",{"key":24,"text":345,"correct":26},"并行施工",{"key":28,"text":347,"correct":26},"增加资源投入",{"key":31,"text":349,"correct":22},"缩小项目范围",{"id":351,"libraryId":5,"type":15,"typeLabel":16,"stem":352,"options":353,"answer":28,"analysis":33},384404,"活动排序是指识别与记载计划活动之间的逻辑关系，项目经理对所管理的项目进行活动排序。（ ）是在活动排序过程中所需要的信息和资料。",[354,356,358,359],{"key":20,"text":355,"correct":26},"项目进度网络图",{"key":24,"text":357,"correct":26},"请求的变更",{"key":28,"text":234,"correct":22},{"key":31,"text":360,"correct":26},"更新的活动清单",{"id":362,"libraryId":5,"type":15,"typeLabel":16,"stem":363,"options":364,"answer":28,"analysis":33},384405,"某项目计划成本为400万元，计划工期为4年，项目进行到两年时，监理发现预算成本为200万元，实际成本为100万元，挣值为50万元，则项目成本偏差为-50万元，项目进度偏差为（）万元。",[365,367,369,371],{"key":20,"text":366,"correct":26},"150",{"key":24,"text":368,"correct":26},"50",{"key":28,"text":370,"correct":22},"-150",{"key":31,"text":372,"correct":26},"-50",{"id":374,"libraryId":5,"type":15,"typeLabel":16,"stem":375,"options":376,"answer":28,"analysis":33},384406,"某项目计划安排为：2014年4月30日完成1000万元的投资任务。在当期进行项目绩效时评估结果为：完成计划投资额的90%，而CPI为50%，这时的项目实际花费为()万元。",[377,379,381,383],{"key":20,"text":378,"correct":26},"450",{"key":24,"text":380,"correct":26},"900",{"key":28,"text":382,"correct":22},"1800",{"key":31,"text":311,"correct":26},{"id":385,"libraryId":5,"type":15,"typeLabel":16,"stem":386,"options":387,"answer":31,"analysis":33},384407,"某公司承接了东北高速铁路信息化建设项目，由于期间可能要接受北方高寒的考验，最好采用（） 进行进度管理。",[388,390,392,394],{"key":20,"text":389,"correct":26},"网络图",{"key":24,"text":391,"correct":26},"资源平衡方法",{"key":28,"text":393,"correct":26},"关键路径法",{"key":31,"text":395,"correct":22},"假设情境分析方法",{"id":397,"libraryId":5,"type":15,"typeLabel":16,"stem":398,"options":399,"answer":31,"analysis":33},384408,"如果项目实施进度比计划提前20%，实际成本只用了预算成本的60%，首先应该（ ）",[400,402,404,406],{"key":20,"text":401,"correct":26},"重新修订季度计划",{"key":24,"text":403,"correct":26},"给项目团队加薪，开表彰大会",{"key":28,"text":405,"correct":26},"重新进行行成本核算",{"key":31,"text":407,"correct":22},"找出最初计划产生差别的原因",{"id":409,"libraryId":5,"type":15,"typeLabel":16,"stem":410,"options":411,"answer":31,"analysis":33},384409,"关键路经法是利用进度计划网络图所进行的一种分析技术，下面关于关键路经的说法中是正确的（）",[412,414,416,418],{"key":20,"text":413,"correct":26},"网络图中只有一条关键路经",{"key":24,"text":415,"correct":26},"关键路经上各活动的时间之和最少",{"key":28,"text":417,"correct":26},"非关键路经上某活动发生延误后项目总工期必然会发生延误",{"key":31,"text":419,"correct":22},"非关键路经上的活动延误时间如果不超过总时差，项目总工期就不会发生延误",{"id":421,"libraryId":5,"type":15,"typeLabel":16,"stem":422,"options":423,"answer":20,"analysis":33},384410,"项目进度表至少包括每项计划活动的计划开始日期与计划完成日期，常见的做法是用一种或多种格式的图形表示。在下面的图表中，常用于表示项目进度表的是()",[424,426,428,430],{"key":20,"text":425,"correct":22},"横道图",{"key":24,"text":427,"correct":26},"排列图",{"key":28,"text":429,"correct":26},"鱼骨图",{"key":31,"text":431,"correct":26},"趋势图",{"id":433,"libraryId":5,"type":15,"typeLabel":16,"stem":434,"options":435,"answer":28,"analysis":33},384411,"以下关于活动资源估算的描述中，错误的是（ ）。",[436,438,440,442],{"key":20,"text":437,"correct":26},"活动资源估算要确定实施项目活动所需资源的使用时间",{"key":24,"text":439,"correct":26},"活动资源估算过程必须和成本估算过程相结合",{"key":28,"text":441,"correct":22},"进行活动排序时需要考虑活动资源估算问题",{"key":31,"text":443,"correct":26},"企业基础设施资源信息可以用于活动资源估算",{"id":445,"libraryId":5,"type":15,"typeLabel":16,"stem":446,"options":447,"answer":24,"analysis":33},384412,"在进行项目活动历时估算时，（）属于参数估算。",[448,450,452,454],{"key":20,"text":449,"correct":26},"从以前类似计划活动的实际持续时间为依据来估算",{"key":24,"text":451,"correct":22},"用需要完成工作的数量乘以完成单位工作所需时间为估算活动时间的依据",{"key":28,"text":453,"correct":26},"利用有可能的历时估算，最乐观的历时估算和最悲观的历时估算来计算",{"key":31,"text":455,"correct":26},"利用以历时信息为依据的专家判断估算",{"id":457,"libraryId":5,"type":15,"typeLabel":16,"stem":458,"options":459,"answer":24,"analysis":33},384413,"某活动的工期采用三点估算法进行估算，其中最悲观估算是23天，最乐观估算是15天，最可能的估算是19天，则该活动的历时大致需要19天，该活动历时方差大概是（）。",[460,462,464,466],{"key":20,"text":461,"correct":26},"0.7",{"key":24,"text":463,"correct":22},"1.3",{"key":28,"text":465,"correct":26},"8",{"key":31,"text":467,"correct":26},"4",{"id":469,"libraryId":5,"type":15,"typeLabel":16,"stem":470,"options":471,"answer":28,"analysis":33},384414,"某公司承接了城市道路信息系统建设项目。由于施工日期正好是7月份的雨季。项目团队为了管理好项目的进度，最好采用（）进行进度管理。",[472,474,475,477],{"key":20,"text":473,"correct":26},"进度比较横道图",{"key":24,"text":391,"correct":26},{"key":28,"text":476,"correct":22},"假设情景分析方法",{"key":31,"text":478,"correct":26},"关键链法",{"id":480,"libraryId":5,"type":15,"typeLabel":16,"stem":481,"options":482,"answer":24,"analysis":33},384415,"在“关键路径上的活动总时差是零和负数”情况下，下列分析正确的是()",[483,485,487,489],{"key":20,"text":484,"correct":26},"关键路径上的活动总时差可能为零的原因是每个相邻活动都是紧前或紧后的，需要调整以给活动留出时间余地",{"key":24,"text":486,"correct":22},"关键路径上的活动总时差可能为负的原因是由于安排调配不得当所造成的活动非合理性交错现象，有必要调整活动持续时间、逻辑关系等使得活动总时差为零",{"key":28,"text":488,"correct":26},"关键路径上的活动总时差可能为负的原因是因为用最早时间减去最晚时间，不需要调整以给活动留出余地",{"key":31,"text":490,"correct":26},"关键路径上的活动总时差可能为零的原因是由于安排活动进度没有余地，需要调整以给活动留出余地",{"id":492,"libraryId":5,"type":15,"typeLabel":16,"stem":493,"options":494,"answer":28,"analysis":33},384416,"以下关于项目进度网络图的描述中，正确的是()",[495,497,499,501],{"key":20,"text":496,"correct":26},"它应该包含项目的全部细节活动",{"key":24,"text":498,"correct":26},"它是活动排序的输入和制定进度计划的输出",{"key":28,"text":500,"correct":22},"前导图法和箭线图法都是绘制项目进度网络图的具体方法",{"key":31,"text":502,"correct":26},"它仅以图形方式展示项目计划活动及逻辑依赖关系，简单直观",{"id":504,"libraryId":5,"type":15,"typeLabel":16,"stem":505,"options":506,"answer":24,"analysis":33},384417,"过去几年小李完成了大量网卡驱动模块的开发，最快6天完成，最慢36天完成，平均21天完成。如今小李开发一个新网卡驱动模块，在21天到26天内完成的概率是()",[507,509,511,513],{"key":20,"text":508,"correct":26},"0.6830000000000001",{"key":24,"text":510,"correct":22},"0.341",{"key":28,"text":512,"correct":26},"0.582",{"key":31,"text":514,"correct":26},"0.281",{"id":516,"libraryId":5,"type":15,"typeLabel":16,"stem":517,"options":518,"answer":31,"analysis":33},384418,"在项目管理中，采取 （ ） 方法，对项目进度计划实施进行全过程监督和控制是经济和合理的。",[519,521,523,525],{"key":20,"text":520,"correct":26},"会议评审和MONTE CARLO分析",{"key":24,"text":522,"correct":26},"项目月报和旁站",{"key":28,"text":524,"correct":26},"进度报告和旁站",{"key":31,"text":526,"correct":22},"挣值管理和会议评审",{"id":528,"libraryId":5,"type":15,"typeLabel":16,"stem":529,"options":530,"answer":20,"analysis":33},384419,"在估算项目中软件开发的工作量时，项目经理按照自己的经验，利用了以下公式：活动历时（软件开发）=5X19XP （P为开发人员的经验系数，19位开发人员的平均工作时间）。该项目经理采用的估算方法是（ ）。",[531,533,535,537],{"key":20,"text":532,"correct":22},"参数估算",{"key":24,"text":534,"correct":26},"类比估算",{"key":28,"text":536,"correct":26},"三点估算法",{"key":31,"text":538,"correct":26},"专家判断",{"id":540,"libraryId":5,"type":15,"typeLabel":16,"stem":541,"options":542,"answer":20,"analysis":33},384420,"某项目有五个独立的子项目，小张和小李各自独立完成项目所需的时间如下表所示：则如下四种安排中 （ ） 的工期最短。",[543,545,547,549],{"key":20,"text":544,"correct":22},"小张做甲和乙，小李做丙、丁和戊",{"key":24,"text":546,"correct":26},"小张做乙，小李做甲、丙、丁和戊",{"key":28,"text":548,"correct":26},"小张做乙、丁和戊，小李做甲和丙",{"key":31,"text":550,"correct":26},"小张做甲、乙和丁，小李做丙和戊",{"id":552,"libraryId":5,"type":15,"typeLabel":16,"stem":553,"options":554,"answer":28,"analysis":33},384421,"某项活动的最早开始日期为本月11日，最晚开始日期是本月19日，该活动的持续时间为4天，如果不涉及非工作日，从上述信息可以判断，（）是正确的。",[555,557,559,561],{"key":20,"text":556,"correct":26},"活动的总体时差为9天",{"key":24,"text":558,"correct":26},"活动的最早完成时间为本月14日",{"key":28,"text":560,"correct":22},"活动的最晚完成时间为本月23日",{"key":31,"text":562,"correct":26},"如果资源分配翻倍，则活动可以在2天完成",{"id":564,"libraryId":5,"type":15,"typeLabel":16,"stem":565,"options":566,"answer":28,"analysis":33},384422,"某项目经理绘制的WBS 局部图如下图所示。 B，C工作包的负责人对人日数进行了估算，依据他们的估算结果，项目经理得出了分项工程A的人日数结果，他采用的是 （ ）方法。",[567,568,570,572],{"key":20,"text":534,"correct":26},{"key":24,"text":569,"correct":26},"自上而下估算",{"key":28,"text":571,"correct":22},"自下而上估算",{"key":31,"text":573,"correct":26},"多方案分析估算",{"id":575,"libraryId":5,"type":15,"typeLabel":16,"stem":576,"options":577,"answer":24,"analysis":33},384423,"进度报告是实施项目进度控制的一个主要工具，在进度报告中可不包括()。",[578,580,582,584],{"key":20,"text":579,"correct":26},"实际开始与完成日期",{"key":24,"text":581,"correct":22},"项目例会的时间",{"key":28,"text":583,"correct":26},"未完成计划活动的剩余持续时间",{"key":31,"text":585,"correct":26},"正在进行的计划活动的完成百分比",{"id":587,"libraryId":5,"type":15,"typeLabel":16,"stem":588,"options":589,"answer":20,"analysis":33},384424,"某工程建设项目中各工序历时如下表所示，通过 （ ） 可以缩短项目工期 ① 压缩B工序时间 ② 压缩H工序时间 ③ 同时开展H工序与A工序 ④ 压缩F工序时间 ⑤ 压缩G工序时间",[590,592,594,596],{"key":20,"text":591,"correct":22},"①⑤",{"key":24,"text":593,"correct":26},"①③",{"key":28,"text":595,"correct":26},"②⑤",{"key":31,"text":597,"correct":26},"③④",{"id":599,"libraryId":5,"type":15,"typeLabel":16,"stem":600,"options":601,"answer":31,"analysis":33},384425,"依据下面的项目活动网络图中，该项目历时为 （ ） 天。",[602,604,606,608],{"key":20,"text":603,"correct":26},"10",{"key":24,"text":605,"correct":26},"11",{"key":28,"text":607,"correct":26},"13",{"key":31,"text":609,"correct":22},"18",[611,615,618,621,624,627],{"id":612,"name":613,"category":7,"favorite":614},136,"法律职业试卷二(客观题 )",2,{"id":616,"name":617,"category":7,"favorite":15},137,"法律职业试卷一(客观题 )",{"id":619,"name":620,"category":7,"favorite":15},176,"（初级）社会工作实务",{"id":622,"name":623,"category":7,"favorite":15},177,"（初级）社会综合能力",{"id":625,"name":626,"category":7,"favorite":8},28,"安全工程师",{"id":628,"name":629,"category":7,"favorite":8},112,"安全生产法律知识"]