[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-385310":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},385310,165,1,"单选题","从信息系统开发的角度来看，信息系统的生命周期包括（）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","立项、开发、运维、消亡",true,{"key":16,"text":17,"correct":18},"B","启动、计划、执行、控制和收尾",false,{"key":20,"text":21,"correct":18},"C","总体规划、系统分析、系统设计、系统实验、系统验收",{"key":23,"text":24,"correct":18},"D","招标、投标、执行合同、合同收尾","【解析】 本题考查信息系统项目生命周期。教程 P82-83。信息系统的生命周期分为四个阶段： 立项（规划）阶段 开发阶段 运维阶段 消亡（更新阶段） 其中开发阶段又分为： ? 总体规划 ? 系统分析 ? 系统设计 ? 系统实施 ? 系统验收",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]