[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-385289":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},385289,165,1,"单选题","系统集成项目通过验收测试的主要标准为 （ ） 。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","所有测试项均未残留各等级的错误",false,{"key":16,"text":17,"correct":18},"B","需求文档定义的功能全部实现，非功能指标达到目标要求",true,{"key":20,"text":21,"correct":14},"C","立项文档、需求文档、设计文档与系统的实现和编码达到一致",{"key":23,"text":24,"correct":14},"D","系统通过单元测试和集成测试","系统通过验收的标准需要以满足用户的需求作为衡量的标准。B包含了用户的需求，其中包含了功能需求、非功能需求和设计约束。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]