[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-385287":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},385287,165,1,"单选题","（）拟订、编制和修订一个项目或项目阶段的工作目标、任务、工作计划方案、资源供应计划、成本预算、计划应急措施等工作。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","启动过程组",false,{"key":16,"text":17,"correct":18},"B","计划过程组",true,{"key":20,"text":21,"correct":14},"C","执行过程组",{"key":23,"text":24,"correct":14},"D","控制过程组","根据PMI的定义共有5个过程组，其中计划过程组拟订、编制和修订一个项目或项目阶段的工作目标、任务、工作计划方案、资源供应计划、成本预算、计划应急措施等工作。这是由一系列项目计划性工作所构成的项目管理具体过程（或阶段\u002F活动）。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]