[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-385284":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},385284,165,1,"单选题","在( )组织结构中,项目没有独立的项目团队,项目经理在调用与项目相关的资源时必需要向职能经理汇报。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","职能型",true,{"key":16,"text":17,"correct":18},"B","平衡矩阵型",false,{"key":20,"text":21,"correct":18},"C","强矩阵型",{"key":23,"text":24,"correct":18},"D","项目型","在组织结构对项目的影响表中，项目经理的权力从小到大，依次是：职能型组织、弱矩阵型组织、平衡矩阵型组织、强矩阵型组织、项目型组织。其中，职能型组织的项目经理的权力很小和没有；而项目型组织结构中，项目拥有独立的项目团队,项目经理在调用与项目相关的资源时不需要向部门经理汇报，权力很大。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]