[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-385237":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},385237,165,1,"单选题","某一MIS系统项目的实施过程如下：需求分析、概要设计、详细设计、编码、单元测试、集成测试、系统测试、验收测试。那么该项目最有可能采用的是（）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","瀑布模型",false,{"key":16,"text":17,"correct":14},"B","迭代模型",{"key":19,"text":20,"correct":21},"C","V模型",true,{"key":23,"text":24,"correct":14},"D","螺旋模型","本题考查V模型的各阶段。《系统集成项目管理工程师教程》的“典型的信息系统项目的生命周期模型”节中V模型示意图（图4-14）中显示：V模型的左边下降的是开发过程各阶段，包括需求分析、概要设计、详细设计和编码。V模型的右边上升的是测试过程的各个阶段，包括单元测试、集成测试、系统测试和验收测试。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]