[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-385216":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},385216,165,1,"单选题","（）seeks to build confidence that a future output or an unfinished output, will be completed in a manner that meets the specified requirements and expectations.",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","Quality assurance",true,{"key":16,"text":17,"correct":18},"B","Quality plan",false,{"key":20,"text":21,"correct":18},"C","Quality control",{"key":23,"text":24,"correct":18},"D","Quality metrics","",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]