[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-385215":3},{"question":4,"library":23},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":22},385215,165,1,"单选题","()is the application of planned，systematic quality activities to ensure thatthe project will employ all processes needed to meet requirements． A.Quality assurance(Q A)",[11,15,19],{"key":12,"text":13,"correct":14},"A","Quality planning",true,{"key":16,"text":17,"correct":18},"B","Quality control(Q",false,{"key":20,"text":21,"correct":18},"C","Quality costs","质量计划是质量管理的一部分，致力于制定质量目标，并规定必要的运行过程和相关资源以实现项目质量目标。质量控制就是项目团队的管理人员采取有效措施，监督项目的具体实施结果，判断它们是否符合项目有关的质量标准，并消除产生不良结果原因的途径。质量成本是指为满足质量要求所付出的主要成本。质量保证是通过对质量计划的系统实施，确保项目需要的相关过程达到预期要求的质量活动。选项 A 是质量保证(QA)，选项B 是质量计划，选项 C 是质量控制(QC)，选项 D 是质量成本。因此应选择 A。",{"id":6,"name":24,"category":25,"favorite":26},"(中级) 系统集成项目管理工程师","职业资格",0]