[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-385210":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},385210,165,1,"单选题","()describees,indetail,the project's deliverables and the work required to create those deliverables.",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","Product scope description",false,{"key":16,"text":17,"correct":14},"B","Project objectives",{"key":19,"text":20,"correct":14},"C","Produce specification",{"key":22,"text":23,"correct":24},"D","The project scope statement",true,"项目范围说明书详细描述了项目的可交付物和提供这些可交付物必须要做的工作。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]