[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-385208":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},385208,165,1,"单选题","All of followings should be done by the project manager during project control except (). A.Determine the a change has occurred",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","Ensure that a change is agreed",false,{"key":16,"text":17,"correct":18},"B","Make sure all changes are approve",true,{"key":20,"text":21,"correct":14},"C","by management",{"key":23,"text":24,"correct":14},"D","Manage changes as they occur","译文：项目经理不应该在项目控制过程中执行的工作是（）。 A)确定变更已经发生 B)确保变更已达成共识 C)确保所有变更都获得管理层批准 D)在变更发生时，对变更进行管理",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]