[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-385204":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},385204,165,1,"单选题","（ ） is primarily concerned with defining and controlling what is and is not included in the project.",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","Project Time Management",false,{"key":16,"text":17,"correct":14},"B","Project Cost Management",{"key":19,"text":20,"correct":21},"C","Project Scope Management",true,{"key":23,"text":24,"correct":14},"D","Project Communications Management","项目范围管理是项目管理（包括时间、成本、沟通）的基础。 项目范围管理是最先定义和决定项目中包含哪些内容和确定边界的。 选项A是项目时间管理，选项B是项目成本管理，选项C是项目范围管理，选项D是项目沟通管理。因此应选择C。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]