[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-385198":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},385198,165,1,"单选题","A project manager believes that modifying the scope of the project may provide added value service for the customer. The project manager should （ ）",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","assign change tasks to project members",false,{"key":16,"text":17,"correct":14},"B","call a meeting of the configuration control board",{"key":19,"text":20,"correct":14},"C","change the scope baseline",{"key":22,"text":23,"correct":24},"D","postpone the modification until a separate enhancement project is fundedafter this project is completed according to the original baseline",true,"项目经理认为调整项目范围可以给客户提供增值的服务，项目经理应该怎么做。 选项A是安排任务变更到项目成员，选项B是召集变更控制委员会会议，选项C是变更项目基线，选项D是按照原先的基线，在确定完成一项改进项目会得到客户的相应资金前，暂缓修改。 由于是在原内容基础上增加增值服务内容，超出原先范围，应先确定客户认可和增加新资金。因此应选择D。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]