[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-385192":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},385192,165,1,"单选题","Project manager believes that modifying the project scope may provide added value for the customer. The project manager should （ ） . A.change the scope baseline",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","contact the customer to determine if the change adds value",false,{"key":16,"text":17,"correct":14},"B","call",{"key":19,"text":20,"correct":21},"C","meeting of the change control board",true,{"key":23,"text":24,"correct":14},"D","change the project’s objectives","",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]