[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-385191":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},385191,165,1,"单选题","In project management, a （ ） is a listing of a project’s milestones ,activities, and deliverables, usually with intended start and finish dates。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","schedule",true,{"key":16,"text":17,"correct":18},"B","activity",false,{"key":20,"text":21,"correct":18},"C","Plan",{"key":23,"text":24,"correct":18},"D","contractor","在项目管理中，（ ）是项目的里程碑、活动和交付物的列表，通常包括开始和完成日期。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]