[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-385186":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},385186,165,1,"单选题","The inputs of developing project management plan do not include（）.",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","project charter",false,{"key":16,"text":17,"correct":18},"B","stakeholder management strategy",true,{"key":20,"text":21,"correct":14},"C","project scope statement",{"key":23,"text":24,"correct":14},"D","outputs from planning processes","制定项目管理计划的输入不包括（72） A.项目章程 B. 干系人管理策略 C.项目范围说明书 D. 计划过程输出",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]