[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-385181":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},385181,165,1,"单选题","A schedule is commonly used in project planning and project portfolio management.（ ） on a schedule may be closely related to the work breakdown structure （WBS）terminal elements, the statement of work, or a contract data requirements list.",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","Essences",false,{"key":16,"text":17,"correct":18},"B","Elements",true,{"key":20,"text":21,"correct":14},"C","Purposes",{"key":23,"text":24,"correct":14},"D","Issues","时间表常用于项目规划和项目组合管理。时间表的元素与工作分解结构（WBS）的最终元素，工作说明书，或合同数据需求清单密切相关。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]