[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-385178":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},385178,165,1,"单选题","The earned value technique is a commonly used method of performance measurement. It integrates project scope, cost, and schedule measures to help the project management team assess project performance. If a project’s Schedule Performance Index（SPI=EV\u002FPV） value less than 1.0, it means that （ ） .",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","he project is ahead of its planned schedule",false,{"key":16,"text":17,"correct":18},"B","less work was completed than was planned t",true,{"key":20,"text":21,"correct":14},"C","the cost overrun for work completed",{"key":23,"text":24,"correct":14},"D","the cost underrun of performance to date","",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]