[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-385177":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},385177,165,1,"单选题","The Perform Integrated Change Control process is conducted from project inception through completion and is the ultimate responsibility of the （ ） .",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","Chang control board",false,{"key":16,"text":17,"correct":14},"B","Project management office",{"key":19,"text":20,"correct":21},"C","Project manager",true,{"key":23,"text":24,"correct":14},"D","Configuration management officer","实施整体变更控制过程是从项目开始到项目结束并且是项目经理的最终责任。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]