[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-385167":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},385167,165,1,"单选题","Project success depends primarily on（） 。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","The quality of the schedule and cost control analysis",false,{"key":16,"text":17,"correct":18},"B","Customer satisfaction",true,{"key":20,"text":21,"correct":14},"C","Customer compromise in defining its needs",{"key":23,"text":24,"correct":14},"D","Exceeding customer requirements through gold-plating","项目的成功依赖于 A.进度计划和成本控制分析的质量 B.客户满意 C.在定义客户需求时客户的妥协 D.通过提供额外服务，超越客户的要求",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]