[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-385166":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},385166,165,1,"单选题","The project schedule is more than a document that lays out the activities over time to represent the time dimension of the project, it is a management tool to be used for decision making. As such , the schedule is used by the project management team to()",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","Measure, delay, record, distribute, analyze, and direct",false,{"key":16,"text":17,"correct":18},"B","Plan, schedule, monitor, control, report, and forecast",true,{"key":20,"text":21,"correct":14},"C","Promote, highlight, monitor, control, forecast, and report",{"key":23,"text":24,"correct":14},"D","Emphasize, visualize, analyze, conceptualize, report and record","项目进度计划不只是一个列出项目规定活动的时间表，而且还是一个用于决策的工具。如：进度计划可以被项目管理团队用来（73）。A.检测，延时，记录，分发，分析和直接B.计划，日程安排，监督，控制，报告和预测C.提升，亮点，监视，控制，预测和报告D.重点化，可视化，分析，概念化，报告和记录",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]