[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-385165":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},385165,165,1,"单选题","Risk management allows the project manager and the project team not to（）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","eliminate most risks during the planning phase of the project",true,{"key":16,"text":17,"correct":18},"B","identify project risks",false,{"key":20,"text":21,"correct":18},"C","identify impacts of various risks",{"key":23,"text":24,"correct":18},"D","plan suitable responses","下面不属于风险管理中项目经理和项目团队职责的是（71）。A.排除大部分项目执行中的风险B.风险识别C.风险分析D.妥善处理",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]