[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-385160":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},385160,165,1,"单选题","Which of the following Project Scope Management processes involves subdividing the major projectdeliverablesinto smaller, more manageable components)()",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","Scope Planning",false,{"key":16,"text":17,"correct":14},"B","Scope Verification",{"key":19,"text":20,"correct":14},"C","Scope Change Control",{"key":22,"text":23,"correct":24},"D","Scope Definition",true,"在以下项目范围管理几个过程中，（74）涉及将主要项目可交付成果细分成更小、更容易管理的组件单元。A.范围规划B.范围确认C.范围变更控制D.范围定义",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]