[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-385141":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},385141,165,1,"单选题","The （）describes, in detail, the project’s deliverables and the work required to create those deliverables.",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","project scope statement",true,{"key":16,"text":17,"correct":18},"B","project requirement",false,{"key":20,"text":21,"correct":18},"C","project charter",{"key":23,"text":24,"correct":18},"D","product specification","项目范围说明书详细描述了项目的可交付物以及为创建这些可交付物所需的工作。 A.项目范围说明书B.项目需求C.项目章程 D.产品规范",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]