[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-385134":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},385134,165,1,"单选题","Schedule development can require the review and revision of duration estimates and resource estimates to create an approved （） that can serve as a baseline to track progress.",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","scope statement",false,{"key":16,"text":17,"correct":14},"B","activity list",{"key":19,"text":20,"correct":14},"C","project charter",{"key":22,"text":23,"correct":24},"D","project schedule",true,"计划进展需要对持续时间和资源的评估和修改创建一个被核准的（74），它可以作为基线，有助于跟踪进展。A.范围说明B.活动列表C.项目章程 D.项目计划",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]