[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-385131":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},385131,165,1,"单选题","The earned value technique is a commonly used method of performance measurement. It integrates project scope, cost, and schedule measures to help the project management team assess project performance. If a project’s Schedule Performance Index（SPI=EV\u002FPV） value less than1.0, it means that_（）.",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","the project is a head of its planned schedule",false,{"key":16,"text":17,"correct":18},"B","less work was completed than was planned",true,{"key":20,"text":21,"correct":14},"C","the cost overrun for work completed",{"key":23,"text":24,"correct":14},"D","the cost under-run of performance to date","挣值技术是一种综合了范围、成本、进度指标的绩效测量方法，帮助项目团队评价项目绩效。如果一个项目的进度绩效指数SPI值小于1，意味着：（74）A．项目滞后B．项目超前C．项目超支D．成本有结余",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]