[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-385130":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},385130,165,1,"单选题","项目具体结果包括项目的最终产品或服务，也包括项目过程的结果。项目过程结果的质量需要由（）进行控制",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","质量控制职能部门",false,{"key":16,"text":17,"correct":14},"B","质检员",{"key":19,"text":20,"correct":14},"C","项目经理",{"key":22,"text":23,"correct":24},"D","项目管理组织的成员",true,"项目具体结果既包括项目的最终产品（可交付成果等）或服务，也包括项目过程的结果。项目产品的质量控制一般由质量控制职能部门负责，而项目过程结果的质量，却需要由项目管理组织的成员进行控制。质量控制过程还可能包括详细的活动和资源计划。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]