[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-385127":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},385127,165,1,"单选题","Risk management’s ( ) is to assure uncertainty does not deflect the endeavor from the business goals",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","trend",false,{"key":16,"text":17,"correct":14},"B","detail",{"key":19,"text":20,"correct":21},"C","objective",true,{"key":23,"text":24,"correct":14},"D","rule","",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]