[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-385126":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},385126,165,1,"单选题","The Project Management Triangle is a model of the constraints of project management. These constraints have been listed scope (or quality), ( ), and cost",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","resource",false,{"key":16,"text":17,"correct":18},"B","time",true,{"key":20,"text":21,"correct":14},"C","plan",{"key":23,"text":24,"correct":14},"D","tool","",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]