[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-385125":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},385125,165,1,"单选题","（）is a method used in Critical Path Methodology for constructing a project schedule network diagram that uses boxes or rectangles, referred to as nodes, to represent activities and connects them with arrows that show the logical relationships that exist between them.",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","PERT",false,{"key":16,"text":17,"correct":14},"B","AOA",{"key":19,"text":20,"correct":14},"C","WBS",{"key":22,"text":23,"correct":24},"D","PDM",true,"（73）用于关键路径法，是用于编制项目进度网络图的一种方法，它使用方框或者长方形（被称作节点）代表活动，它们之间用箭头连接，显示彼此之间存在的逻辑关系。A.PERT B. AOAC. WBS D. PDM",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]