[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-385123":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},385123,165,1,"单选题","() is not the advantage of GERT （Graphical evaluation and review techniques）as compared with PERT （project evaluation and review techniques）.",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","Allowing looping",false,{"key":16,"text":17,"correct":18},"B","Allowing for dummy tasks",true,{"key":20,"text":21,"correct":14},"C","Allowing branching",{"key":23,"text":24,"correct":14},"D","Allowing multiple project end results","与PERT（计划评审法）相比（）不是GERT（图表评审法）的优势。A、允许循环B、允许虚活动C、允许分支D、允许多个项目的最终结果",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]