[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-385103":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},385103,165,1,"单选题","某信息系统集成项目实施期间，因建设单位指定的系统部署地点所处的大楼进行线路改造，导致项目停工一个月，由于建设单位未提前通知承建单位，导致双方在项目启动阶段协商通过的项目计划无法如期履行。根据我国有关规定，承建单位 （ ） 。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","可申请延长工期补偿，也可申请费用补偿",true,{"key":16,"text":17,"correct":18},"B","可申请延长工期补偿，不可申请费用补偿",false,{"key":20,"text":21,"correct":18},"C","可申请费用补偿，不可申请延长工期补偿",{"key":23,"text":24,"correct":18},"D","无法取得补偿","",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]