[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-385079":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},385079,165,1,"单选题","某政府部门拟利用中央财政资金建设电子政务项目，关于建设方的立项管理，下列说法中不符合有关规定的是 （ ） 。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","建设单位在编制项目建议书时专门组织项目需求分析，形成需求分析报告，报送项目审批部门",false,{"key":16,"text":17,"correct":14},"B","建设方在项目建议书获得批复后，招标选定有资格的第三方工程咨询机构编制可行性研究报告，报送项目审批部门",{"key":19,"text":20,"correct":21},"C","建设方在可行性研究报告获得批复后，向有关部门申请项目前期工作经费，前期工作经费计入项目总投资",true,{"key":23,"text":24,"correct":14},"D","建设方在可行性研究报告获得批复后，委托有资格的第三方工程咨询机构出具评估意见，连同批复的项目建议书，作为项目建设的主要依据","",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]