[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384952":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},384952,165,1,"单选题","在信息系统试运行阶段，系统失效将对业务造成影响。针对该风险，如果采取“接受”的方式进行应对，应该（）",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","签订一份保险合同，减轻中断带来的损失",false,{"key":16,"text":17,"correct":14},"B","找出造成系统中断的各种因素，利用帕累托分析减轻和消除主要因素",{"key":19,"text":20,"correct":14},"C","设置冗余系统",{"key":22,"text":23,"correct":24},"D","建立相应的应急储备",true,"风险管理、收尾管理、知识产权管理",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]