[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384940":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},384940,165,1,"单选题","以下关于定性风险分析的描述中，不正确的是()",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","定性风险分析需要考虑风险发生的概率及其后果的影响性",false,{"key":16,"text":17,"correct":18},"B","实施定性风险分析的方法中包括SWOT分析法",true,{"key":20,"text":21,"correct":14},"C","通常情况下技术含量越高的项目，其风险程度也越高",{"key":23,"text":24,"correct":14},"D","定性风险分析的工作成果之一是按优先级形成风险总排队","SWOT分析法只用在风险识别过程中。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]