[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384928":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},384928,165,1,"单选题","某项目承包者预计该项目有 0.5 的概率获利 200000 美元,0.3 的概率亏损 50000 美元,还有 0.2 的概率维持平衡.该项目的期望货币价 值为( )美元。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","200000",false,{"key":16,"text":17,"correct":18},"B","85000",true,{"key":20,"text":21,"correct":14},"C","50000",{"key":23,"text":24,"correct":14},"D","180000","",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]