[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384927":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},384927,165,1,"单选题","在项目执行阶段，一名团队成员识别了一项新风险，此时，应该 （ ） 。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","将之涵盖在风险触发因素中",false,{"key":16,"text":17,"correct":14},"B","对假设条件进行测试",{"key":19,"text":20,"correct":14},"C","将之加入风险管理计划内",{"key":22,"text":23,"correct":24},"D","对风险进行定性分析",true,"",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]