[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384924":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},384924,165,1,"单选题","某集成企业在进行风险定性分析时，考虑了风险的几种因素：①威胁，指风险对项目造成的危害程度；②机会，指对项目带来的收益程度；③紧迫性，对风险亟待处置的程度；④风险发生的概率。关于该公司的定性风险分析，下列说法中，()是不正确的。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","①×③×④的值越大，则表明风险高，应考虑优先处理",false,{"key":16,"text":17,"correct":14},"B","②×③×④的值越大，则表明机会大，应考虑优先处理",{"key":19,"text":20,"correct":21},"C","①×②×④的值越大，则表明风险高、机会大，应考虑优先处理",true,{"key":23,"text":24,"correct":14},"D","②×④的值越大，则表明机会大，应考虑优先处理","依题意 ①×②×④的值越大，则表明风险高、机会大，应考虑优先处理 。不对，应该是①×②×④的值越大，则表明威胁大、机会大，应考虑优先处理 。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]