[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-384917":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},384917,165,1,"单选题","决策树分析是风险分析过程中的一项常用技术。某企业在项目风险分析过程中，采用了决策树分析方法，并计算出了EMV（期望货币值）。以下说法中，正确的是（）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","以上进行的是定量风险分析，根据分析结果应选择修改现有技术方案的路线",true,{"key":16,"text":17,"correct":18},"B","以上进行的是定量风险分析，根据分析结果应选择设计新技术方案的路线",false,{"key":20,"text":21,"correct":18},"C","以上进行的是定性风险分析，根据分析结果应选择修改现有技术方案的路线",{"key":23,"text":24,"correct":18},"D","以上进行的是定性风险分析，根据分析结果应选择设计新技术方案的路线","风险管理、收尾管理、知识产权管理",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 系统集成项目管理工程师","职业资格",0]